Define Us.

Kutaisi Bypass
Completed · 2021

Kutaisi Bypass Motorway
— Lot 4

km 30+000 – km 41+354

Client: Georgian Roads Department, under the Ministry of Infrastructure of Georgia

~6M EUR Value
11.354 km Length
Apr 2018 – Aug 2021 Duration
250 Employees

Modernization of the Kutaisi Bypass Road – Samtredia Section into a four-lane motorway. Works included 745,000 m³ of earthworks, 6,930 m² of bridges, and 4,500 m of pile works.

Samtredia Grigoleti
Completed · 2023

Samtredia – Grigoleti
Motorway — Lot 1

km 0+000 – km 11+500

Client: Georgian Roads Department, under the Ministry of Infrastructure of Georgia

~6.3M EUR Value
11.5 km Length
Dec 2021 – Sep 2023 Duration
120 Employees

Construction of a new four-lane motorway in western Georgia. Works included 32,175 m² of bridges and 4,500 m of pile works.

Tsereteli Street
Completed · 2022

Kutaisi — Tsereteli Street
Rehabilitation

2.8 km urban road rehabilitation

Client: Georgian Roads Department, under the Ministry of Infrastructure of Georgia

~1.6M EUR Value
32,500 m² Asphalt Area
Sep 2020 – May 2022 Duration
50 Employees

Rehabilitation of one of the main streets in Kutaisi city, restoring surface quality and drainage across 2.8 km of urban road.